Roles of Team Members in Agile Projects

Roles of Team Members in Agile Projects

What if you applied Scrum to a real-world SI project?

The roles of PMs, PLs, planners, developers, and customers—and how to run Sprints

In the previous post, we explored concepts such as Scrum, empiricism, and pair work, along with the 12 principles of Agile.

So how can you apply Agile to a real-world SI project?

SI projects, in particular, have characteristics that set them apart from typical product development.

They have a fixed contract period, a client, and a defined budget and scope. They also require deliverables for each phase, such as analysis, design, development, and testing.

Therefore, a practical approach is not to completely abandon the framework of an existing SI project, but to incorporate the strengths of Scrum into it.

In this post, we’ll create a hypothetical SI project and look at how to apply Scrum in practice.

1. Let’s Create a Hypothetical SI Project

For example, let’s assume a company has commissioned the following project.

Project name: Next-Generation Customer Management System Implementation

The project will run for six months.

The main features are as follows.

  • Login

  • User management

  • Customer information management

  • Product management

  • Order management

  • Payments

  • Statistics and reports

  • Administrator system

  • Integration with external systems

A traditional SI approach might follow roughly these phases:

Analysis → Design → Development → Testing → Launch

However, by applying some Agile practices, you can break the entire project into smaller development units and work through them incrementally.

For example, a two-week period can be run as one Sprint.

2. First, Define the Project Roles

Scrum has three core roles: Product Owner, Scrum Master, and Developers.

However, real-world SI projects involve various job titles that differ from company to company, such as PMs, PLs, planners, developers, and client representatives.

So you need to align Scrum roles with the existing roles in SI projects in a way that works for your team.

For example, you could organize the roles as follows.

Traditional SI role

Role from a Scrum perspective

Client business representative

Product Owner role

PM

Overall project management and coordination

PL

Development team leadership and technical decision-making

Planner/analyst

Requirements organization and support for Backlog management

Developer

Developers

QA

Quality assurance and testing

Scrum Master

The PM or a separate person in charge can perform this role

The important thing here is that job titles and Scrum roles do not necessarily have to correspond one-to-one.

3. Who should be the Product Owner?

This is one of the most challenging aspects of an SI project. The Product Owner is not simply someone who communicates requirements.

They are responsible for deciding what to build first and maximizing the value of the product.

Therefore, ideally, the Product Owner should be someone who knows the client's actual business operations well, rather than an employee of the development company.

For example, someone from the client's Customer Management Team Leadcould take on the role of Product Owner.

When the development team asks, “Which should we develop first, Feature A or Feature B?”

the Product Owner should be able to set priorities by saying, “Feature A is essential for our work this month, so please develop it first.”

4. Create a Backlog

Instead of finalizing every feature in excessive detail at the beginning of the project, manage all requirements in a Product Backlog.

For example:

Product Backlog

  1. Login

  2. Sign up

  3. User management

  4. Register customer

  5. View customer

  6. Edit customer

  7. Register product

  8. View product

  9. Create order

  10. View order

  11. Payment

  12. Statistics

  13. Admin functions

  14. Integration with external systems

What matters here is priority. Not all features are equally important.

For example, if the customer says, “The statistics screen is important too, but registering and viewing customers are the most urgent,” then increase the priority of customer registration and viewing.

5. Hold Sprint Planning

Now, let's start the first Sprint. Assume that the Sprint duration is set to two weeks.

In the first Sprint, the development team selects the following features:

Sprint 1

  • Login

  • Sign up

  • Basic user information

  • Basic screen layout

The important point here is that the PM does not unilaterally assign tasks to developers; instead, the team determines how much work it can handle during the Sprint.

For example, the PL determines, “We should be able to complete this much in this Sprint,” and the development team puts together the Sprint Backlog.

6. Carry out development within the Sprint

Once the Sprint begins, the development team develops the selected features.

For example

Day 1

Set up the development environment and database

Days 2–3

Develop the login API

Days 4–5

Develop the login screen

Day 6

Develop the sign-up feature

Days 7–8

Develop user information features

Day 9

Integration

Day 10

Testing and revisions

You can proceed this way.

The important thing here is not simply writing code.

By the end of the Sprint, you need to have a feature that actually works.

7. The Daily Scrum is not a “status report”

Hold a short Daily Scrum every day, lasting about 10–15 minutes.

It’s not a meeting where developers report to the PM; it’s an opportunity for the team to share the current status.

For example, rather than having Developer A say, “I’m developing the login feature,”

it’s much more important to share: “The login API is complete, but we’ve run into a problem integrating with the external authentication server. If we can’t resolve this, it could affect the Sprint goal.”

That’s because identifying problems early allows the team to respond immediately.

8. Use pair work for challenging features

There’s no need for two people to work together on every development task.

However, pair work can be used for important features.

For example, let’s say you’re developing a payment feature.

Instead of Developer A working on it alone,

A + B

work together on the design and development.

One person writes the code while the other reviews it alongside them. The benefit of this approach is more than just reducing errors.

It can prevent knowledge about a particular feature from being concentrated in a single developer.

For example, even if A goes on vacation, B can understand the code and handle any issues.

It’s especially effective to use this selectively for features such as:

  • Payments

  • Security

  • Core business logic

  • Complex SQL

  • Large-scale data processing

  • Integration with external systems

  • Shared modules

9. Show customers the actual system at the Sprint Review

After two weeks, the Sprint ends. The Sprint Review is important at this point.

Rather than having the development team show documents and explain, “The login feature is complete,”

it’s better to show the actual system.

For example, have the customer representative try it out themselves:

Sign up → Log in → View member information → Edit member information

They try it out.

During the process, the customer might say, “I don’t think this field is necessary during sign-up.”

Or you could say, “Our employees often use it this way rather than using this screen.”

This is what Agile calls feedback.

10. What if the customer's requirements change?

This is where the difference between the traditional SI approach and the Agile approach becomes apparent.

Let's say the customer requests, “We'd like to change the layout of the sign-up screen.”

In a traditional project, the first issue that may arise is, “The requirements have changed, so this will affect the schedule and cost.”

In Agile, first, register the change request in the Backlog.

Then the Product Owner determines its priority.

For example,

change request A

Change the sign-up screen

existing requirement B

the administrator statistics feature,

the Product Owner might decide that “changing the sign-up screen is more important.”

Then, in the next Sprint, the team can develop A first and lower the priority of B.

Of course, if the change falls outside the scope of the actual SI contract, separate discussions about change management, schedule, and costs are needed.

Being Agile does not mean ignoring the realities of contracts and costs.

11. Hold a Sprint Retrospective

After the Sprint Review, the team holds an internal retrospective.

The questions are simple:

What went well?

For example:

Communication between developers improved.

What didn't go well?

Development was delayed because the API specifications were finalized late.

What should we change in the next Sprint?

Finalize the API specifications before the Sprint starts.

It is important to apply at least one concrete improvement in the next Sprint.

If every retrospective ends with “Let's do better next time,” then Agile has no meaning.

12. Apply what you've learned in Sprint 2

The team learns a lot during the first Sprint.

For example:

  • Testing took longer than expected.

  • The customer's requirements differed from the documentation.

  • Too much work was assigned to one particular developer.

  • Integrating with external systems took a lot of time.

The team applies these lessons to the second Sprint.

This is what is known as empiricism.

Rather than creating a perfect plan from the start,

try it out → review the results → adjust the next plan

.

13. How should a six-month project be managed?

For example, assuming a six-month project uses two-week Sprints, you can run about 12 Sprints.

Early in the project

Sprint 0

Development environment, architecture, and basic design

Sprints 1–3

Member/customer management

Sprints 4–6

Products/orders

Sprints 7–9

Payments and external systems

Sprints 10–11

Statistics and admin features

Sprint 12

Integration testing and stabilization

Of course, in an actual project, the Sprint duration and structure may vary depending on the nature of the project.

14. The PM’s role becomes even more important

Some people think that adopting Agile eliminates the PM’s role.

The opposite is true.

In an SI project, the PM must manage

the overall schedule + contracts + costs + customers + organization + risks

...

Especially in an Agile environment, rather than asking, “Why didn’t things go according to plan?”

you need to determine, “Given the current situation, how can we achieve the project goals?”

In other words, the PM is not simply a schedule manager, butis responsible for making decisions across the project and aligning stakeholdersas part of the role.

15. The PL is responsible for the development team’s technical direction

A PL should not simply be someone who assigns tasks to developers.

Especially in an Agile environment, they need to manage

  • technical decisions

  • architecture

  • code quality

  • technical risks

  • collaboration among developers

  • technical debt

and other areas. When needed, they should also encourage knowledge sharing among developers through Pair Work or Code Review.

16. The planner’s role also changes

In an Agile project, the planner’s role may shift from creating every screen perfectly from the outset and handing it over to developers.

It is important for the planner to understand customer requirements andbreak them down into small, implementable units.

For example,

the broad requirement, “Please build a customer management system,” can be broken down into:

  • Register a customer

  • View customers

  • View customer details

  • Edit a customer

  • Delete a customer

  • Search customers

  • Customer history

Break them down into small features, and determine the priority of each one.

17. The Developer’s Role Also Changes

In traditional SI, developers may easily think, “This is the screen I’m responsible for.”

But in Agile,

“What goal should the team achieve in this Sprint?”is the question they need to ask.

Therefore, collaboration that goes a little beyond the boundaries of each developer’s responsibilities is necessary.

A developer’s responsibility for the project doesn’t end just because their assigned work is finished;

they can also support another developer’s work or help with testing.

This is a way of working that puts the team before the individual.

18. The Three Most Important Things When Applying Agile in SI

If I were to apply Agile to an actual SI project, I think the following three things would be most important.

First: Show actual results in short cycles

Don’t just create documents; show a system that actually works.

Analysis → Development → Verification → Feedback

The goal is to make this cycle as short as possible.

Second: Involve the customer in the project

It’s difficult to apply Agile if the customer provides requirements at the start of the project and receives the deliverables at the end.

The customer needs to continuously

review → use → give feedback → determine priorities

throughout the project.

Third: Make real changes based on retrospectives

The key to Agile isn’t repeating Sprints.

It’s for the team to keep improving as it repeats Sprints.

Therefore, improvements identified in a retrospective should actually be applied in the next Sprint.

Conclusion

Applying Agile to an SI project doesn’t mean you have to get rid of everything from existing PM practices, deliverables, contracts, and schedule management.

Rather, a practical approach is to retain the strengths of existing SI projects while combining them with the strengths of Agile.

For example:

PM

→ Manages the overall project schedule, costs, contracts, and risks

Product Owner

→ Determines customer requirements and priorities

PL

→ Sets the technical direction and manages the development team

Planner

→ Breaks requirements down into small development units

Developer

→ Collaborates to achieve the Sprint goal

Customer

→ Reviews actual deliverables and provides ongoing feedback

And this entire process is repeated in the following cycle.

Backlog

↓

Sprint Planning

↓

Development

↓

Daily Scrum

↓

Working Software

↓

Sprint Review

↓

Customer Feedback

↓

Retrospective

↓

Improvement

↓

Next Sprint

Ultimately, the essence of Agile

is not “creating a perfect plan from the start,”
but “executing quickly, learning from actual results, and continuously improving”That’s what it comes down to.

This approach is especially valuable in SI projects, where there is a lot of change and many complex stakeholders.